Last week, the contractor completed the northerly section of
storm sewer, including all storm sewer services, from the homes between 957
Prairie Lawn/934 Rolling Pass to 921 Prairie Lawn/906 Rolling Pass.
The contractor has also completed all of the tree trimming,
removal, or transplanting as necessary to access the site. The contractor has
also removed the required fencing and other landscaping items required to
complete the project.
The contractor also started on the southerly section of the
storm sewer improvements at 911 Prairie Lawn/902 Rolling Pass and will be
working south towards Linneman Street.
It is anticipated the work in these rear-yards will take
another 2-3 weeks to complete. The progress is slower than anticipated due to
the tight conditions they were working in and only able to access to site from
the south at Linneman Street. As they
continue to move south, the progress should become quicker because there is
less travel from their singular access point to the location they are
installing the storm sewer.
Thank
you again to all the residents who have been dealing with the construction in
the back yards for the past 2 weeks. This past week was especially difficult
due to the amount of rain and made the work area very sloppy. Please be assured the Village is working with
the contractor to ensure the work is progressing as quickly as possible with
the least amount of disruption. The contractor is responsible for restoring landscaping
items that are disrupted during the construction process.